Farnborough Pool & Spa Upgrade

Farnborough Pool & Spa Upgrade

Summary of project

After reviewing the design of the pool plant strategy it was decided that the filtration system in place was not sufficient to open the facility. Working closely with the De Vere Group DFM provided a scope of work that seen the removal of all existing filters and pumps to be replaced with new GRP 1m deep bed sand filters and plastic housed pumps to suit the required volumes. DFM project managed and overseen the installation of the improved filtration system which also included the installation of Ultra Violet (UV) units for both the pool and spa areas to support the standard disinfection system.

What was done?

DFM tendered and managed the project through to completion and final commissioning, after which the project was successfully opened.